CONSTRUCTION LAYURI CHAÑOCAGUA SAYTHU COMMUNITY DRINKING WATER SYSTEM

8 Jun
FAMILIES THAT BENEFIT FROM THE PROJECT 278
CURRENT AREA OF ​​INFLUENCE 464 Ha
AREA UNDER OPTIMAL IRRIGATION 485 Ha
AREA UNDER OPTIMAL FUTURE IRRIGATION 785 Ha
OBJECTIVE OF THE PROJECT gGuarantee the availability of water to improve the agricultural and livestock production system, which allows raising the productive level, contributing to the improvement of the quality of life of the beneficiary population of the project, through the commercialization of surplus production, ensuring food security with sovereignty for the well-being of the community’s population
  Achieved goals
  • Construction of a water collection work for irrigation, with its infrastructure complementary
  • Construction of 26.13 km of pipeline networks for irrigation in the community of Tacuara, for conduction and distribution of water for irrigation plot level according to the following characteristic
  • Laying of 5964.05 meters of Pipe. PVC 14″ C-9, C-12, C-15, C-18
  • Laying of 1978.56 meters of Pipe. PVC 12″ C-9, C-12, C-15, C-18
  • Laying of 7721.02 meters of Pipe. PVC 10″ C-9, C-12, C-15, C-18
  • Laying of 4928.49 meters of Pipe. PVC 6″ C-9, C-12, C-15, C-18
  • Laying of 2043.94 meters of Pipe. PVC 4″ C-9, C-15, C-18
  • 01 hectares under irrigation in this first intervention to ensure agricultural production and livestock in the community
  • The Irrigators’ Organization has its management instruments for distribution operation and maintenance of the Irrigation System
  • management training, operation, maintenance of the irrigation system drip technology and alternatives organic fruit production
  • Families receive technical assistance in the process project execution